Between I-84; I-84B Bliss and 1000 East Road (1 mile east of the Bliss area). Road construction work is in progress. Bridge construction work is in progress. The road is being repaved. The roadway is reduced to one lane. The left lane is closed. Expect delays. Look out for temporary traffic lights. Speed restrictions are in force. There is a width limit in effect. Expect 5 - minute delays. Speed limit 35 MPH. Width limit 12'0". Until April 1, 2021 at about 5:00PM MST.
Web Comment: eplacing box canal. Temporary traffic lights will be operating for duration of project.
Contractor: Cannon Builders
Traffic Control: Specialty Constr
ITD Contact: Tom Logan 208-886-7800
Last updated yesterday at 7:15pm MST