Truck Restrictions on I-90
I-90

Between Exit 15: Sherman Avenue and Exit 13: 4th Street (Coeur d'Alene). Look out for long term road construction work. Bridge construction work is in progress. A lane is closed. There is a width limit in effect. Look out for traffic congestion. Speed limit 55 MPH. Until September 29, 2020 at about 5:30PM PDT.

Web Comment: Work to replace the Pennsylvania Ave bridges begins in March. For more details visit itdprojects.org/i90pennsylvania. Width restriction is 19'.

Last updated on July 6

Between Exit 14: 15th Street and Exit 15: Sherman Avenue (Coeur d'Alene). Look out for long term road construction work. Bridge construction work is in progress. A lane is closed. Look out for traffic congestion. Speed limit 55 MPH. Width limit 13'0". Until September 29, 2020 at about 5:30PM PDT.

Web Comment: Work to replace the Pennsylvania Ave bridges begins in March. For more details visit itdprojects.org/i90pennsylvania

Last updated on July 6

Between Exit 17: Mullan Road and Exit 22: ID 97 (2 to 5 miles east of the Coeur d'Alene area). Bridge construction work is in progress. Road construction work is in progress. The roadway is reduced to one lane. Speed limit 55 MPH. Width limit 14'0". Until August 31, 2020 at about 7:00PM PDT.

Web Comment: median cross-over will be in use. Current traffic pattern will remain through the 4th of July Weekend. After the 4th of July Weekend work will shift to the Westbound Bridge. Eastbound traffic will be crossed over to the eastbound structure.

Last updated on July 7

Between Exit 48: Airport Road and Exit 54: Big Creek Road (near Kellogg). Road maintenance work is in progress. The left lane is closed. Advisory speed limit 45 MPH. Width limit 14'0". Until today at about 3:00PM PDT.

Last updated yesterday at 7:14pm PDT