US 30
US 30 in both directions: Road construction, paving operation, roadway reduced to one lane, reduce your speed, width limit in effect, look out for flagger, pilot car in operation, seal coat, loose gravel. Speed limit 40 MPH. Width limit 14'0".

Between 1350 East Road (near Buhl) and 2100 East Road (near Filer). Road construction work is in progress. The road is being repaved. The roadway is reduced to one lane. Reduce your speed. There is a width limit in effect. Look out for flaggers. A pilot car is in operation. A seal coat treatment has been applied. Look out for loose gravel on the roadway. Speed limit 40 MPH. Width limit 14'0". Until June 30, 2021 at about 7:00PM MDT.

Web Comment: The roadway is being repaved with chip sealing to occur when paving is complete. Use caution around crews and equipment.

Last updated on May 27
US 30 eastbound: Height limit in effect. Height limit 13'5".

Between Main Street - Hawthorne Road and Cedar Street (Pocatello). There is a height limit in effect. Height limit 13'5".

Web Comment: This is a permanent height restriction within the city limits of Pocatello, in both east and westbound lanes, at the railroad bridge on Garret Way, between Main Street and Cedar Street, at milepost 334.15.

Last updated on May 21
US 30: Height limit in effect. Height limit 13'7".

Between Main Street - Hawthorne Road and Cedar Street (Pocatello). There is a height limit in effect. Height limit 13'7".

Web Comment: There is a permanent height restriction within the city limits of Pocatello, affecting both eastbound and westbound travel.

Last updated on May 21
Switch to Winter Driving Conditions
Switch to Road Reports
Truck Restrictions on US 30
Map of Reports on US 30 Between 1350 East Road (near Buhl) and 2100 East Road (near Filer). Road construction work is in progress. The road is being repaved. The roadway is reduced to one lane. Reduce your speed. There is a width limit in effect. Look out for flaggers. A pilot car is in operation. A seal coat treatment has been applied. Look out for loose gravel on the roadway. Speed limit 40 MPH. Width limit 14'0". Until June 30, 2021 at about 7:00PM MDT. Between Swan Lake Road (5 miles east of the Soda Springs area) and Georgetown Summit (3 miles west of the Georgetown area). The roadway is reduced to one lane. A pilot car is in operation. Speed restrictions are in force. Expect delays. Expect 10 - minute delays. Until June 29, 2021 at about 11:59PM MDT.
US 30 in both directions: Road construction, paving operation, roadway reduced to one lane, reduce your speed, width limit in effect, look out for flagger, pilot car in operation, seal coat, loose gravel. Speed limit 40 MPH. Width limit 14'0".
US 30 eastbound: Height limit in effect. Height limit 13'5".
US 30: Height limit in effect. Height limit 13'7".
US 30: Fish Creek
Google Static Map Image
Closure Closure Restriction Restriction Spring Breakup Spring Breakup