Idaho Transportation Department Logo Idaho Transportation Department   Highway Info
This website will transition to a NEW 511 site. Start using it NOW!
Truck Restrictions on US 95
US 95

Between Toney Lane and Salubria Road (near Cambridge). There is a width limit in effect. The roadway is reduced to one lane. Bridge construction work is in progress. Expect delays. There is work on the shoulder. Width limit 12'0". Expect 10 - minute delays. Until November 30, 2021 at about 11:59PM MDT.

Web Comment: Expect 10 minutes delays. Restricted to one lane starting 4/26 with width restriction of 12'

Last updated today at 12:02pm MDT

Between Hot Springs Road and The Little Salmon River Bridge (near New Meadows). Road construction work is in progress. The road is being repaved. Look out for bridge demolition work due to bridge construction work. The roadway is reduced to one lane. Expect delays. There is a width limit in effect. Width limit 14'0". Until November 8, 2021 at about 5:00PM MDT.

Last updated yesterday at 6:47am MDT

Between Marina Drive and Walnut Avenue (Coeur d'Alene). A lane is closed because of construction work. Width limit 12'0". From 7:00PM PDT to 5:00AM PDT on Tuesday, Wednesday and Thursday. Until tomorrow at about 5:00AM PDT.

Web Comment: One lane traffic at night only. Lane closures will be allowed only between 7:00 pm and 5:00 am, Tuesday night April 20, Wednesday night April 21 and Thursday night April 22. Both lanes open during the day. Work will be complete Friday morning, April 23 by 5:00 am.

Last updated on April 12

Between 1st Street and Granite-Kelso Cut-Off Road (1 to 4 miles north of the Athol area). Road construction work is in progress due to road work. The right lane is closed. Speed limit 55 MPH. Width limit 16'0". From 7:00AM PDT to 5:00PM PDT on weekdays. Until December 31, 2022 at about 5:00PM PDT.

Web Comment: Adding a Right lane Closure intermittently as work needs it. Reconstruction of US-95 and Frontage roads. Most work will occur off alignment for building the East side Frontage Road. Once complete US-95 Traffic will be crossed over onto the newly built frontage road until mainline and the west side frontage road is complete. Scheduled for two years of construction.

Last updated yesterday at 7:48am PDT