Idaho Transportation Department Logo Idaho Transportation Department   Highway Info
Reports on ID 11
ID 11
Between US 12 and Woodland Grade Road (16 miles south of the Weippe area). Bridge construction work is in progress. Expect delays. There is a width limit in effect. Expect 15 - minute delays. Width limit 11'0". Until October 7, 2019 at about 6:00PM PDT.
Between Mill Road and Green Road (3 miles south of the Weippe area). Road construction work is in progress. The road is being repaved. Bridge construction work is in progress. There is work on the shoulder. The roadway is reduced to one lane. Expect delays. Look out for flaggers. There is a width limit in effect. Expect 15 - minute delays. Width limit 11'0". Until November 18, 2019 at about 8:00PM PDT.